WELLHEAD MAINTENANCE (FIRST AND SECOND LINE) AT THE OTAKIKPO MARGINAL FIELD, OML 11
Nondera Energy Services was awarded the first-line and second-line maintenance of two dual-completion wellheads (OTK 2 and OTK 3) at the Otakikpo Marginal Field by the field’s joint venture. Each wellhead has a long string and a short string, so the work covered four production strings. Each string has its own Christmas tree valves, downhole safety valve and hydraulic control unit.
First-line maintenance. Our team inspected every wellhead, tubing hanger and Christmas tree, then function-tested and pressure-tested each string. Tests covered the swab, flow wing and master valves, the surface safety valve, the surface-controlled subsurface safety valve, the X-bushing, the tubing hanger and control line integrity. Test pressures reached 4,500 psi. We also checked annulus pressures and inspected for external leaks at gaskets, seals and packing. Findings were recorded on a standard “as found / as left” wellhead reporting sheet.
Second-line (corrective) maintenance. The inspection found faulty components, and we repaired them:
- Replaced faulty 2-9/16″ gate and seat assemblies on both OTK 2 and OTK 3
- Replaced the actuator top-sub seal on the OTK 2 short string
- Replaced faulty pilot isolation valves on the OTK 2 and OTK 3 control panels
- Serviced the OTK 2 control unit, including draining and refilling its hydraulic oil
- Replaced the drain valves on both arms of the OTK 3 control unit pump
- Replaced the 1/2″ test valves (KTV) on the OTK 2 and OTK 3 short strings
Each repair was function-tested, and the OTK 3 master valve was leak-tested to confirm it held pressure.